Architect of the Capitol's R.C. "Skip" Vaughn, Capital Projects Administrator, gives a quick project update from the building utilities phase of the Cannon Renewal.

As part of the Cannon Renewal Project, the team is using ground penetrating radar (GPR) to plan and execute its work. GPR drawings (like the above) help workers see what's inside the concrete of the Cannon Building's garage and moat walls. The project team's structural engineers are then able to identify exactly what a worker may potentially hit behind that area of concrete and determine the best way to relocate holes and minimize their impacts. The project team is able to use the GPR drawings to precisely locate existing reinforcing steel and utilities, avoiding potentially costly and time-consuming corrective measures from drilling through these types of items unknowingly.

Image

A GPR drawing on a concrete wall in the Cannon Building's courtyard.

This practice, along with the use of fully coordinated 3D building information model drawings, helps to ensure we minimize the amount of historic fabric disturbed while installing the new utility systems for the Cannon Building.

Add new comment

The content of this field is kept private and will not be shown publicly.

Plain text

  • No HTML tags allowed.
  • Lines and paragraphs break automatically.
  • Web page addresses and email addresses turn into links automatically.

Our Stories

Recent Articles

Projects

House Hearing Room Renovation

Rayburn Room 2172 recently underwent renovations that include a refurbished wall-to-wall audiovisual (AV) system, a custom dais and several improved accessibility features.
Projects

A House for All Seasons

More than 140 years later, the Architect of the Capitol's Summerhouse still offers visitors respite. Recent maintenance efforts will help keep the site around for repeat visitors and first timers alike.